Dornan worked on the redevelopment of the iconic Broadgate Circle Arena, including retail units, ancillary service areas and the Number 3 Broadgate Building, while retaining and upgrading the base build structures. Construction works were carried out while maintaining full basement access to the adjacent financial institutions. The project achieved a BREEAM rating of ‘very good’.
Mechanical works included
- Above-ground drainage ventilation
- Smoke extract system
- BMS
- Dry air coolers
- Chillers
- Heating plant
- Fans
- Motorised smoke fire dampers
- Grille attenuators
- Heating and cooling pipework
- Insulation
- Pre-fabricated risers and services modules, 3D coordination, commissioning
Electrical works included
- Electrical switchboards
- Sub-mains cabling
- Small power
- Lighting and lighting control
- EMS
- Fire alarm
- Disabled refuge
- Trace heating containment
- Commissioning