Project Description
Dornan were awarded the Main Electrical contract in 2019 for this mission critical DC project located in Denmark. The project involved delivery of the full electrical services both at MV & LV to allow for the successful turnover of the 60MW Facility. The project peaked at a resource level of 450No. Operatives and achieved 600,000+ Hours worked safely and without an LTI. The project utilised both in country specialist contractors and supply chain from neighbouring European countries. The project excelled on quality and as a result achieved its FR status with a Zero defect status.
Scope of Works
Early contractor involvement to support Design Development, Constructability studies, coordination
activities.
MV/LV Services installation – Containment, Cabling, Termination, Testing.
Supply, Installation and commissioning of the Bus Bar System.
Electrical equipment installed included transformers, associated back-up generators and back up
UPS systems.
Supply, Installation and commissioning of the Security, Fire, Voice Evacuation, Smoke Damper,
Emergency Lighting systems.
Management of the COHE/LOTO systems on site.
10 Eastgate Avenue,
Eastgate,
Little Island,
Cork T45 PC63
"*" indicates required fields
Unit A7
Centrepoint Business Park,
Oak Road,
Dublin 12
D12 YE 16
"*" indicates required fields
114a Cromwell Road,
Kensington,
London SW7 4ES
"*" indicates required fields
c/o Regus
Teleport Towers
Kingsfordweg 151
1043 GR Amsterdam
"*" indicates required fields
Antwerp
Uitbreidingstraat 84/3,
2600 Berchem,
Belgium
"*" indicates required fields
Regus Express
Copenhagen Airport
Terminal 3, 4th Floor
2770 Kastrup
"*" indicates required fields
Regus Norra Bantorget,
Olof Palmes gata 29,
Stockholm,
Sweden
"*" indicates required fields
Wilbecker Strasse 18,
D-40699 Erkrath
Germany
"*" indicates required fields
C/O J09 Lonza, Lonzastrasse 2,
CH-3930, Visp, Switzerland