Tata Steel, Port Talbot

Dornan won three separate contracts for work on replacing Blast Furnace 4 at Port Talbot. We were one of the largest contractors on the project, operating on a 24/7 basis, with as many as 285 personnel on site and 200,000 man-hours completed.

Works included

  • c 15,000m of primary containment
  • MV installations
  • In-air monitoring system
  • Clear call system
  • Hazard warning system
  • Instrumentation, cabling and junction boxes installation
  • Local control stations and safety switches
  • Electrical cabling terminations
  • Lighting & small power installation
  • Earthing supply, cabling and terminations
  • Electrical heat tracing
  • Electrical pre‐commissioning motor testing