To meet growing demand for its Ellipta inhaler, GSK needed a new three-floor manufacturing facility alongside its existing facility at Ware in Hertfordshire. The new 4500ft2 facility has nearly doubled production capacity, with around 95% of output for export. Dornan completed a range of instrumentation and electrical works.
Instrumentation responsibilities included
- Junctions boxes, local panels and analyser panels installation
- Cable trays installation
- Instrument multi-cables laying and connection
- Instrument cabinets installation
- Calibration, tests and loop checks
Electrical responsibilities included installation of
- Lighting system
- Telephone system
- Cable trays
- Cables and connections
- Electrical heat tracing system