Pier D Dublin Airport

Client:Dublin Airport Authority
Country:Ireland
Completed:2008
Programme:October 2006 to March 2008
Project Description:
Supply and Installation of Complete Electrical Services on the New Pier ‘D’ and Link Bridge. The Total Area of the Project was 19,228 m2 which included the Link Bridge, Arrivals & Departures Areas and 12 Loading Gates.
Scope of Works:
  • Lighting
  • Lighting Control
  • Data/Comms
  • Power
  • HV installation
  • Window controls
  • Building Management System controls
  • Security
  • Access Control
  • CCTV
  • Emergency Lighting Systems
  • Back Up generator system
  • UPS systems
  • Fire Alarm
  • Gas Suppression System